Long-term single lane traffic on Route 30 in the area of the bridges over Electric Avenue (Route 2112) in North Braddock and Chalfant boroughs begins this Thursday.

Single lane closures in each direction will begin at approximately 9 a.m. Crews will be constructing a temporary crossover in the median. Work to construct the crossover will take about three weeks. Once this work is complete, traffic on eastbound Route 30 will be crossed over on the westbound lanes. Traffic will remain a single lane in each direction on the westbound lanes through late November while crews reconstruct the eastbound bridge.

The $12.9 million project includes replacing the bridges over Electric Avenue, bituminous pavement, approach work, drainage, guide rail and concrete barrier, highway lighting, retaining wall and other improvements.

Find out what's happening in Forest Hills-Regent Squarewith free, real-time updates from Patch.

The overall project will be completed in fall 2013. The prime contractor is the Trumbull Corporation of Pittsburgh.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from Forest Hills-Regent Square